Showing posts with label Structal. Show all posts
Showing posts with label Structal. Show all posts

Tuesday, December 6, 2011

B.C. Place's multimillion-dollar legal fiasco

A very messy legal battle is unfolding over the controversial $563 million renovation of B.C. Place Stadium, home of the Grey Cup champion B.C. Lions and the Major League Soccer chump Whitecaps.

Quebec-based steel supplier Canam Group slapped French cable specialist Freyssinet with a $26.15 million countersuit on Nov. 18. Read all about it here.

Canam's Structal division was responsible for the steel masts. It hired Freyssinet to supply and install the cables for the new retractable roof. Quite simply, the two companies couldn't get along. Now they're pointing fingers at the other, alleging bad management and shoddy workmanship.

This lawsuit has been festering since April, when Canam informed shareholders of a major cost overrun. B.C. Pavilion Corporation claimed it wouldn't cost taxpayers more, because the contract was fixed-price. This is what I reported then.

This is what I reported in August, as the reopening of the stadium rapidly approached and construction was going around the clock.

If you followed any of the roof leaks and box office and food and beverage service troubles during the reopening, the root cause of the rocky reopening was the Canam/Freyssinet conflict.

Had erection of the steel masts and attachment of the cables gone smoothly and according to schedule, the roof would have been fully installed by the start of summer and game day staff would have had several weeks of training inside the building before the Sept. 30 reopening. Workers could have leisurely done their best to make the new roof leak-proof, while days were long, sunny and dry.

Read the key court filings below.

Though unproven and untested in court, these filings lead to more questions than answers about the risky renovation.

What did PavCo and general contractor PCL know about the dispute?

When did they know the two important subcontractors were encountering major difficulties?

Why did taxpayers have to wait until lawsuits were filed to learn about these problems?

How much will the stadium ultimately cost taxpayers?

B.C. Place renovation lawsuit: Freyssinet Statement of Claim

B.C. Place renovation lawsuit: Canam Response

B.C. Place renovation lawsuit: Canam Counterclaim

B.C. Place renovation lawsuit: PavCo Response

Monday, November 7, 2011

More roof problems at B.C. Place




More trouble for B.C. Place Stadium, where the Sept. 30 reopening was anything but smooth.

The French headquartered cable erection company hired by a Quebec steel subcontractor is suing for almost $6.5 million. B.C. Pavilion Corporation, the taxpayer-owned stadium’s operator, is named as a defendant.

Freyssinet filed a lawsuit in British Columbia Supreme Court on Oct. 31, charging Canam with breach of contract, breach of statutory trust and equitable fraud. Problems have been festering for many months. Here's my update from Aug. 4.

PCL Constructors and Canam Group were awarded a $122,864,581 contract on Nov. 18, 2009, according to the Freyssinet court filings. Canam hired Freyssinet as a subcontractor for $30,124,377, “but were unable to agree on all terms.”

"Nevertheless, Freyssinet commenced work on the improvement in July 2010 and on Aug. 23, 2010, Canam and Freyssinet signed a subcontract, backdated to Nov. 20, 2009," said the lawsuit. "However the subcontract was signed without Canam and Freyssinet agreeing on the cost of the erection work budget."

Freyssinet claims Canam failed to keep work on schedule, directed labour and equipment without Freyssinet’s knowledge or consent, interfered with Freyssinet foremen and “permitted rates from Montacier International, a company related to Canam, for labour for erection of the cable which were higher than agreed upon.”

Canam announced in November 2010 that it would “follow an alternate method of erection of the cable, without consulting with Freyssinet and without Freyssinet’s consent.”

"Through 2010, payments were made by Canam on account of the invoices, but Canam then wrongfully ceased making payment to Freyssinet."

Freyssinet says it is owed $6,466,892 by Canam, which claims Freyssinet owes it $24,137.756.44.

A Sept. 29, 2011 letter by Canam alleged: "Due to Freyssinet's negligence in preparation of the cost budget and the construction methodology, there was a significant cost overrun which Canam was required to bear in the fixed price contract with PCL."

"Canam intentionally and wrongfully made the demand to recover alleged damages for financial losses arising from the completed work. This was a wrongful, tortious act constituting equitable fraud."

As of Oct. 19, certificates of completion had not been issued for the head contract. The stadium reopened Sept. 30.

The Freyssinet claims have not been tested in court. I am waiting for responses from Canam and PavCo.

Blog Archive